Quantity Surveying Contracts & Tenders (QSCT) SPPU Endsem Question Paper Nov 2025
All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.
- Subject code
- 401012
- Pattern
- 2019 pattern
- Exam
- Endsem
- Session
- Nov 2025
- Max. marks
- 70
- Time
- 3 Hours
- Semester
- VIII
- Paper code
- [6584]-54
Instructions to the candidates
- Answer Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8.
- Neat diagrams must be drawn wherever necessary.
- Figures to Right indicate full marks.
- Use of electronic pocket calculator is allowed.
- Assume suitable data if necessary.
Questions
Q1
- a)[6]
Explain different methods of taking out quantities. Explain any one with example.
- b)[12]
Figure shows plan and section of residential building, Determine the quantities of following item By PWD Method (Assume any suitable data) i) Excavation in foundation ii) PCC in Foundation iii) UCR masonry in CM (1 : 6) in foundation iv) CR masonry in CM (1 : 6) in foundation v) Damp proof course 3 cm thick 2
OR- a)
Q2
- a)[9]
Determine quantity to steel reinforcement in slab for both room from figure clear cover on both side 20 mm (Assume any suitable data)
- b)[9]
R.C.C simply supported beam of side 300 mm × 400 mm is shown in figure The span of beam is 6.0 m and end bearing (both sides) is 30 cm. calculate total quantity of steel reinforcement. (Assume any suitable data)
- a)
Q3
- a)[8]
Differentiate between following methods : i) Mid sectional area method & Mean Sectional area method. ii) Trapezoidal formula method & Prismoidal formula method.
- b)[10]
This part has equations that don’t show as text. Open the PDF to read it.
OR- a)
Q4
- a)[8]
List out different methods to workout Earth work quantity for road work. Explain any one method.
Also asked:Nov 2023
- b)[10]
Prepare an estimate of a pipe culvert for following item as shown in Fig. 4 (a) and Fig. 4(b) i) Excavation ii) Earth filling iii) Rubble soling
- a)
Q5
ORQ6
- a)[9]
Prepare a rate analysis of Cement concrete 1:2:4 for R. C. C. Roof Slab with 2.5 % steel.
- b)[8]
Prepare a detailed Specification for plain cement concrete & Brick Masonry in Superstructure. 4
Also asked:Nov 2023
- a)
Q7
- a)[6]
Why do depreciation occur in the valuation of property? What are the different methods of calculating depreciation. Explain any one method of calculating depreciation stating formula used, merits & demerits.
- b)[5]
- c)[6]
A building is constructed at a cost of 10 lakhs. The life of building may be assumed to be 90 years and the scrap value of building to be 10% of building cost. Determine the depreciation in 60 th year. Use straight line method, sinking fund method assuming 10% compound interest.
OR- a)
Q8
- a)[6]
Differentiate between Cost, Price & Value with suitable example.
Also asked:May 2023
- b)[5]
Define the following terms : i) Dual rate Year purchase ii) Sinking Fund iii) Annuity iv) Obsolescence v) Free hold Propert
- c)[6]
This part has equations that don’t show as text. Open the PDF to read it.