Skip to content
EndsemMay 20252019 patternBE Civil

Quantity Surveying Contracts & Tenders (QSCT) SPPU Endsem Question Paper May 2025

All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.

Subject code
401012
Pattern
2019 pattern
Exam
Endsem
Session
May 2025
Max. marks
70
Time
3 Hours
Semester
VIII
Paper code
[6404]-68

Printed for: B.E. (Civil)

Instructions to the candidates

  1. Answer Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8.
  2. Neat diagrams must be drawn wherever necessary.
  3. Figures to the right indicate full marks.
  4. Use of electronic pocket calculator is allowed.
  5. Assume suitable data if necessary.

Questions

  1. Q1

    1. a)

      Describe in detail the concepts of the PWD method and the Centre Line method, using examples for better understanding.

      [6]
    2. b)

      Figure shows plan and section of residential building, Determine the quantities of following item (PWD method) i) Excavation in Foundation ii) PCC in Foundation iii) UCR masonry in CM (1 : 6) in foundation iv) CR masonry in CM (1 : 6) in foundation v) Damp proof course 3 cm thick 2

      [12]
  2. Q2

    1. a)

      The plan and elevation for the column footing for an R.C.C. framed structure is shown in Figure work out the quantities for the following item of works. i) Earth work excavation for foundation ii) Cement Concrete (1:2:4) for column footing

      [10]
    2. b)

      Explain the terms i) Bar Bending Schedule ii) Types of Steel reinforcement iii) Weight of Steel Bar iv) Number of Bars or Stirrups

      Also asked:Nov 2023

      [8]
  3. Q3

    1. a)

      Differentiate between following methods i) Mid sectional area method & Mean Sectional area method. ii) Trapezoidal formula method & Prismoidal formula method. 3

      Also asked:Nov 2025 ·May 2024 ·Nov 2023

      [8]
    2. b)

      Following fig. shows the levels plotted for a road work. The formation level of a road at starting point is 370. The road surface shall be falling gradient line of 1 to 60. Formation width of a road = 10 m, side slopes 1:2 in embankment and 1.5:1 in cutting. Assume that there is no cross slopes to the ground. i) Calculate the formation level of all points ii) Calculate the quantity of earthwork in embankment iii) Calculate the quantity of earthwork in cutting

      [10]
  4. Q4

    1. a)

      Explain different method to work out quantity of earthwork for Canal, Railway Embankent & Dam.

      Also asked:Nov 2024 ·May 2024 ·May 2023

      [8]
    2. b)

      Prepare an estimate of a pipe culvert for following item as shown in Fig. 4(a) and Fig. 4(b) i) Excavation ii) Earth filling iii) Rubble soling Fig. 4(a) Fig. 4(b) 4

      [10]
  5. Q5

    1. a)

      Using the standard format, conduct the rate analysis for the following item of work. Brickwork in a cement mortar 1:6. (take brick size as 19cm × 9 cm × 9cm)

      Also asked:May 2024 ·May 2023

      [9]
    2. b)

      Write a detailed specification for RCC work in superstructure.

      [8]
  6. Q6

    1. a)

      Write a detailed specification for BBM in CM 1:6 for superstructure.

      Also asked:Nov 2024 ·May 2023

      [9]
    2. b)

      What is task work? Why does it vary? Explain how the task work is useful in rate analysis of an item.

      [8]
  7. Q7

    1. a)

      A building is constructed at a cost of ` 30,00,000. The estimated useful life of the building is 70 years, and its residual (scrap) value at the end of its life is expected to be 10% of the original cost. Calculate the amount of depreciation for the 40 th year using the following methods : i) Straight Line Method ii) Diminishing Balance Method (Constant Percentage Method)

      [6]
    2. b)

      What do depreciation occur in the valuation of property.

      [5]
    3. c)

      Identify six major factors that impact the assessment of property value, and explain it.

      [6]
  8. Q8

    1. a)

      This part has equations that don’t show as text. Open the PDF to read it.

      [6]
    2. b)

      Explain the concept of free hold and lease hold property. What are the reasons under which the property is leased and what are the liabilities of leaser and lease?

      Also asked:Nov 2024 ·May 2023

      [5]
    3. c)

      Explain the following terms : i) Belting method of land valuation ii) Sinking Fund Method 

      [6]