Quantity Surveying Contracts & Tenders (QSCT) important questionsMost repeated in SPPU papers
These 24 questions appeared in more than one SPPU Quantity Surveying Contracts & Tenders paper we have: 9 papers, from Feb 2023 to Nov 2025. The most-asked come first. Each one links to the papers it was asked in.
Repeated questions
Endsem questions (19)
- 4×asked
- 4×asked
- 3×asked
A building is constructed at a cost of 10 lakhs. The life of building may be assumed to be 90 years and the scrap value of building to be 10% of building cost. Determine the depreciation in 60 th year. Use straight line method, sinking fund method assuming 10% compound interest.
- 3×asked
- 3×asked
- 3×asked
- 3×asked
- 3×asked
- 3×asked
Calculate the quantities of earthwork for 200 m length for a portion of road in an uniform ground, the height of banks at two ends being 1.0m and 1.60m. The formation width is 10 m and side slope 2:1 (H:V). Assume that there is no transverse slope. Use 3 different methods
- 3×asked
- 3×asked
- 2×asked
- 2×asked
- 2×asked
- 2×asked
- 2×asked
- 2×asked
- 2×asked
- 2×asked
Insem questions (5)
- 2×asked
Determine approximate estimated cost of a residential building using following data: i) Built up area of the proposed building = 350 sq.m. ii) Cost of construction for a building of built up area 300 sq.m and with same specification as proposed building constructed 3 years before = Rs: 16,00,000/- iii) Assume 24% rise in construction cost over rates before three years. iv) Assume a provision of 15% of construction cost for water supply, drainage and electrification.
- 2×asked
- 2×asked
- 2×asked
- 2×asked
Questions count as repeated when their wording matches closely across papers. Numericals that depend on a figure are left out, since the figure changes from paper to paper.