Quantity Surveying Contracts & Tenders (QSCT) SPPU Insem Question Paper Mar 2025
All 4 questions from this SPPU insem paper, as printed. Read them here or open the PDF.
- Subject code
- 401012
- Pattern
- 2019 pattern
- Exam
- Insem
- Session
- Mar 2025
- Max. marks
- 30
- Time
- 1 Hour 15 min.
- Semester
- VIII
- Paper code
- [6411]-27
Printed for: BE. (CIVIL) (INSEM)
Instructions to the candidates
- Answer Q1. Or Q2, & Q3 Or Q4.
- Neat diagrams must be drawn wherever necessary
- Figures to the right indicate full marks.
- Use of electronic pocket calculator is allowed
- Assume suitable data if necessary.
Questions
Q1
- a)[5]
Draw a standard format of measurement form and abstract form.
- b)[5]
Determine approximate estimated cost of a residential building using following data: i) Built up area of the proposed building = 350 sq.m. ii) Cost of construction for a building of built up area 300 sq.m and with same specification as proposed building constructed 3 years before = Rs: 16,00,000/- iii) Assume 24% rise in construction cost over rates before three years. iv) Assume a provision of 15% of construction cost for water supply, drainage and electrification.
Also asked:Mar 2024
- c)[5]
Write short note on prime cost and provisional cost of items.
OR- a)
Q2
- a)[5]
Enlist data required to prepare estimate and explain in detail.
Also asked:Mar 2024
- b)[5]
Write short note on contingencies and rate analysis.
- c)[5]
Explain Bay method and Service unit method for preparing approximate estimate. 2
- a)
Q3
- a)[5]
State various method of inviting tenders and explain any one method.
- b)[5]
Explain five conditions of contract related to the execution of work. Give appropriate examples.
- c)[5]
What is arbitration and what are powers of arbitrator?
Also asked:Mar 2024
OR- a)
Q4
- a)[5]
What is meant by a tender notice? Discuss the essential contents of a typical tender.
- b)[5]
Define contract and what are the objectives of it?
- c)[5]
Explain the role of Arbitrator in civil engineering works.
- a)