Quantity Surveying Contracts & Tenders (QSCT) SPPU Endsem Question Paper May 2024
All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.
- Subject code
- 401012
- Pattern
- 2019 pattern
- Exam
- Endsem
- Session
- May 2024
- Max. marks
- 70
- Time
- 3 Hours
- Semester
- VIII
- Paper code
- [6263]-68
Printed for: B.E. (Civil)
Instructions to the candidates
- Answer Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8.
- Neat diagrams must be drawn wherever necessary.
- Figures to the right indicate full marks.
- Use of electronic pocket calculator is allowed.
- Assume suitable data if necessary.
Questions
Q1
- a)[8]
What are the factors to be considered while preparing detailed estimates?
- b)[9]
Determine the quantity of steel reinforcement in slab for both room from fig in 8mm φ bar provided @120mm c/c along short & long span with alternate bent up bar, determine the quantity of reinforcement.
OR- a)
Q2
- a)[8]
Fig shows plan and section of residential building determine the quantities of following item by PWD method (assume any suitable data) i) Excavation in foundation ii) Pcc in foundation iii) UCR masonry in cm (1:6) in foundation 2 iv) Damp proof coarse 3cm thick.
- b)[9]
Explain in detail concept of long wall short wall and Centre line method with the help of example.
- a)
Q3
- a)[8]
Calculate for an embankment by mean area method workout the qualities of earthwork for an embankment 100m long and 10m width at the top side slope 2:1 and the depth of each 20m and are 0.6, 1.2, 1.4, 1.6, 1.5 m respectively.
- b)[9]
Differentiate between following methods : i) Mid sectional area method & mean sectional area method ii) Trapezoidal formula & Prismoidal formula
OR- a)
Q4
- a)[9]
Calculate the quantities of earthwork foe 200m length for portion of road in the uniform ground the height of banks at two ends being 1.0m and 1.60m. the formation width is 10m and side slope is 2:1 (H:V). assume that there is no transverse slope.
- b)[8]
Explain different methods to work out the earthwork quantity for roads and canals. 3
- a)
Q5
ORQ6
- a)[9]
Draft a detailed specification for materials, labour, workshop, mode of measurement etc. for the UCR masonry in foundations and plinth.
- b)[9]
Explain the factors to be considered while determining rate per unit of an item.
- a)
Q7
- a)[6]
- b)[6]
Discuss five factors that affect the value of property.
- c)[6]
What is depreciation? List the different methods of calculating depreciation. Explain any one
Also asked:May 2023
ORQ8
- a)[6]
State four methods of computing depreciation. Explain any one in details.
- b)[6]
Explain the concept of freehold and lease hold property.