Industrial Engineering SPPU Endsem Question Paper Nov 2025
All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.
- Subject code
- 402044D
- Pattern
- 2019 pattern
- Exam
- Endsem
- Session
- Nov 2025
- Max. marks
- 70
- Time
- 2½ Hours
- Semester
- VII
- Paper code
- [6584]-223
Printed for: B.E. (Mechanical)
Instructions to the candidates
- Solve Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8.
- Figures to the right indicate full marks.
- Use of electronics calculator is allowed.
- Assume suitable data, if necessary.
Questions
Q1
- a)[9]
Sketch and explain in brief Material flow patterns & the Selection criterion for material handling.
- b)[8]
Explain in detail factors affecting selection of location for the industrial plant.
Also asked:May 2025
OR- a)
Q2
Q3
- a)[8]
What is Line balancing? Explain Assembly line balancing in detail.
- b)[9]
Calculate the forecast for February to July for trading firm Rudra industries which uses exponential smoothing with smoothing constant 0.18 for estimating a demand. Following table shows the demand for 6 months. The forecast for January is 550 units. Month Actual Demand January 480 February 520 March 525 April 498 May 477 June 564 2
OR- a)
Q4
- a)[8]
Write a short on i) Master production schedule ii) Capacity Planning
- b)[9]
This part has equations that don’t show as text. Open the PDF to read it.
- a)
Q5
- a)[9]
- b)[9]
Explain the term EOQ. A production company requires 9500 units per year. Ordering cost is Rs. 130 per order & carrying cost is 21%. Purchase price per unit is Rs. 48. Determine i) EOQ ii) Optimum no. of orders iii) Total cost including acquisition of material.
ORQ6
- a)[9]
Explain the role of material management in Cost Reduction & Value Improvement. Explain the term “MRP-I”.
Also asked:Nov 2022
- b)[9]
The rajesh enterprises use EOQ logic to determine the order quantity for its. various components and are planning its orders. The Annual consumption is 90,000 units, Cost to place one order is Rs.1200, Cost per unit is Rs.50 and carrying cost is 7% of Unit cost. Find, i) EOQ & No. of order per year, ii) Ordering Cost and Carrying Cost iii) Total Cost of Inventory.
- a)
Q7
- a)[10]
Explain Key result area in detail. What is value engineering? Explain steps in value analysis.
- b)[8]
OR- a)
Q8