Industrial Engineering SPPU Insem Question Paper Aug 2025

All 4 questions from this SPPU insem paper, as printed. Read them here or open the PDF.

Subject code
402044D
Pattern
2019 pattern
Exam
Insem
Session
Aug 2025
Max. marks
30
Time
1 Hour
Semester
VII
Paper code
[6580]-563

Printed for: B.E. (Mechanical) (Insem)

Instructions to the candidates

  1. Solve Q.1 or Q.2, Q.3 or Q.4.
  2. Figures to the right indicate full marks.
  3. Use of electronic calculator is allowed.
  4. Assume suitable data, if necessary.

Questions

  1. Q1

    1. a)

      Summarize different productivity improvement methods? Elaborate 5 “S” system in brief with its benefits?

      Also asked:Sep 2023

      [7]
    2. b)

      Explain the term industrial engineering? What is its importance? Also explain PDCA chart in details.

      [8]
  2. Q2

    1. a)

      Explain the term Productivity? Also explain any two Productivity Measurement Models.

      Also asked:Sep 2024

      [8]
    2. b)

      ABC Company Produces 1600 kg of Spanners by consuming 2200 kg mix of raw material for a particular period. For the next period, the output is 3400 kg by consuming 4350 kg of the raw material and for the third period, the output is increased to 3600 kg by consuming 4450 kg of raw material. Comment on increase or decrease of productivity for Second & Third period.

      Also asked:Sep 2023

      [7]
  3. Q3

    1. a)

      Explain different types of recording techniques used in method study? Also explain Two handed process chart with suitable example.

      [7]
    2. b)

      Following are the recorded times of a machining operation. The corresponding rating and relaxation allowances are given below calculate Normal Time & standard time. 2 Element Observed Performance Relaxation Allowance Time (Min) rating (%) 1 0.15 85 13 2 0.05 85 13 3 0.55 90 10 4 1.00 95 12 5 0.1 90 13

      [8]
  4. Q4

    1. a)

      Explain the term “Performance rating”? Illustrate different performance rating Methods?

      [7]
    2. b)

      The work study engineer carried out the work sampling study. The following observations were made for a machine shop The time duration of study = 120 hrs Total number of observations = 7000 Number of working activities = 1200 Ratio between manual to a machine elements 2:1 Average rating factor 120% Total no. of jobs produced during study = 800 Units Rest and personal time for the job = 12% 

      Also asked:Sep 2023

      [8]