Power System Operation & Control (PSOC) SPPU Endsem Question Paper Nov 2023

All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.

Subject code
403141
Pattern
2019 pattern
Exam
Endsem
Session
Nov 2023
Max. marks
70
Time
2½ Hours
Semester
VII
Paper code
[6181]-125

Printed for: B.E. (Electrical Engineering)

Instructions to the candidates

  1. Solve Q.1 or Q.2; Q.3 or Q.4; Q.5 or Q.6; Q.7 or Q.8.
  2. Figures to the right indicate full marks.
  3. Neat diagrams must be drawn wherever necessary.
  4. Assume suitable additional data, if necessary.
  5. Use of a non-programmable calculator is allowed.

Questions

  1. Q1

    1. a)

      Comment on : The necessity of automatic generation control.

      Also asked:Nov 2025

      [4]
    2. b)

      Explain following concepts i) Control area concept ii) Area control error

      Also asked:May 2025 ·May 2024

      [6]
    3. c)

      Explain the working of the speed governor system of the turbo generator with a schematic diagram.

      Also asked:Nov 2025 ·May 2025

      [8]
  2. Q2

    1. a)

      Draw the complete transfer function block diagram representing single are load frequency control including the speed governing model, turbine model and generator load model.

      [4]
    2. b)

      Draw and explain the complete block diagram of proportional and integral load frequency control of an isolated power system.

      Also asked:May 2025 ·Nov 2024 ·May 2023

      [6]
    3. c)

      Explain the steady state analysis of single area load frequency control along with its block diagram and two cases: Case i) When the speed changer has a fixed setting and load demand is varying Case ii) When load demand is fixed and the speed changer setting is varying

      [8]
  3. Q3

    1. a)

      Explain the heat rate curve and cost curve of a thermal generating unit.

      Also asked:May 2025 ·Nov 2024 ·May 2024 ·May 2023

      [4]
    2. b)

      Discuss the economic scheduling of thermal plants (method of Lagrange’s multiplier) neglecting the effect of transmission losses.

      [6]
    3. c)

      This part has equations that don’t show as text. Open the PDF to read it.

      [7]
  4. Q4

    1. a)

      Discuss hydro constraints and thermal constraints used for Unit Commitment.

      [4]
    2. b)

      Discuss the economic scheduling of thermal plants considering the effect of transmission losses.

      [6]
    3. c)

      This part has equations that don’t show as text. Open the PDF to read it.

      [7]
  5. Q5

    1. a)

      What is power system interconnection? State its advantages.

      Also asked:Nov 2025 ·May 2024 ·May 2023 ·Nov 2022

      [4]
    2. b)

      Explain the operation of power pools.

      [6]
    3. c)

      Explain the following type of power interchange: Diversity Interchange.

      [8]
  6. Q6

    1. a)

      Explain in detail: Capacity Interchange.

      [4]
    2. b)

      Write a short note on Interchange evaluation with unit commitment.

      Also asked:Nov 2025 ·May 2025 ·May 2024 ·May 2023 ·Nov 2022

      [6]
    3. c)

      Comment on : i) Inadvertent Power Exchange ii) Energy Banking

      [8]
  7. Q7

    1. a)

      Draw the QV curve with appropriate labeling showing stable and unstable regions.

      Also asked:Nov 2025 ·May 2025 ·May 2023 ·Nov 2022

      [4]
    2. b)

      What happens when there is voltage instability in the power system? Explain in detail.

      Also asked:Nov 2025 ·May 2023 ·Nov 2022

      [6]
    3. c)

      Why voltage stability study has to gain importance in the power system study? Explain.

      [7]
  8. Q8

    1. a)

      Draw the PV curve with appropriate labeling showing a stable-unstable region.

      Also asked:Nov 2025 ·May 2025 ·May 2023 ·Nov 2022

      [4]
    2. b)

      What observations were obtained from the PV curve? Enlist the disadvantages of the PV curve.

      [6]
    3. c)

      Give the detailed classification of the voltage stability based on the time frame and based on nature of the disturbance. 

      Also asked:Nov 2025 ·May 2025 ·Nov 2022

      [7]