Electrical Installation Design & Condition Based Maintenance SPPU Endsem Question Paper May 2024
All 8 questions from this SPPU endsem paper, as printed. Read them here or open the PDF.
- Subject code
- 303144
- Pattern
- 2019 pattern
- Exam
- Endsem
- Session
- May 2024
- Max. marks
- 70
- Time
- 2½ Hours
- Semester
- I
- Paper code
- [6262]-65
Printed for: T.E. (Electrical Engineering)
Instructions to the candidates
- Answer Q.1 or Q.2, Q.3 or Q.4, Q.5 or Q.6, Q.7 or Q.8.
- Figures to the right indicate full marks.
- Neat diagrams must be drawn wherever necessary.
- Assume suitable additional data, if necessary.
- Use of non - programmble calculator is allowed.
Questions
Q1
ORQ2
- a)[4]
- b)[6]
Explain the process of condition monitoring of on load tap changer.
- c)[8]
How transformer oil gets contaminated? With suitable diagram explain the reconditioning process of transformer oil.
Also asked:Nov 2025
Q3
ORQ4
Q5
- a)[4]
Write a short note on Current carrying Capacity for conductor size calculations.
Also asked:Nov 2025
- b)[6]
Write down all rules for residential wiring work.
- c)[8]
Explain the procedure of installation of underground LT service line.
OR- a)
Q6
- a)[4]
Write a short note on Voltage Drop for conductor size calculations.
Also asked:Nov 2025
- b)[6]
Explain various residential wiring methods with diagrams.
- c)[8]
A single room house receives supply voltage of 200 V. Length of wire from switch fuse unit to the working point is 33 meters. The current requirement is only 5 Ampere. Referring standard table find suitable size of conductor so that voltage drop is within the limit.
- a)
Q7
ORQ8